The procedure for restoring main electrical power to the ship's busbars following a blackout, carried out as rapidly and safely as possible using the emergency generator, batteries, and standby generator auto-start facilities, followed by controlled re-energization of priority consumers to restore propulsion, steering, essential machinery, and safety systems. The sequence typically involves: confirming the cause of the blackout and ensuring it is safe to re-energize; starting the emergency generator (if not already auto-started); starting a main generator, synchronizing it to the emergency bus or energizing the dead bus; then progressively connecting loads in order of operational priority while monitoring generator loading to avoid an immediate repeat overload trip.